SMI42

42 Smith St Duplex

42 Smith St, Marrickville NSW 2204

$1074258.49spent
Budget: $887000.00$187,258 over
74 invoices121% used
FRAMINGis $12500.00 over budget (113%)
CERTIFIERis $52545.46 over budget (757%)
ARCHITECTis $25000.00 over budget (171%)
BRICKWORKis $1000.00 over budget (102%)
KITCHENis $9500.00 over budget (121%)
UTILITIESis $21909.10 over budget (210%)
DEMOis $1000.00 over budget (103%)
ENGINEERis $12200.00 over budget (181%)
SURVEYis $3000.00 over budget (160%)
PLUMBINGis $500.00 over budget (99%)
ELECTRICALis $0.00 over budget (100%)
EXCAVATIONis $1500.00 over budget (97%)
WINDOWSis $0.00 over budget (100%)
PLASTERis $500.00 over budget (99%)
HVACis $0.00 over budget (100%)
PAINTINGis $0.00 over budget (100%)
LANDSCAPEis $0.00 over budget (100%)
TILINGis $500.00 over budget (98%)
FLOORINGis $500.00 over budget (98%)
WATERPROOFis $0.00 over budget (100%)
11 invoices pending review

Cost Breakdown

33 codes
Cost CodeBudgetSpentRemainingProgress
FRAMINGFraming - Structural(4)$95000.00$107500.00-$12500.00
113%
CERTIFIERCouncil & Certifier Fees(3)$8000.00$60545.46-$52545.46
757%
ARCHITECTArchitect & Design(2)$35000.00$60000.00-$25000.00
171%
BRICKWORKBrickwork & Cladding(3)$55000.00$56000.00-$1000.00
102%
KITCHENKitchen & Joinery(3)$45000.00$54500.00-$9500.00
121%
UTILITIESUtility Connections(4)$20000.00$41909.10-$21909.10
210%
DEMODemolition & Site Clear(3)$35000.00$36000.00-$1000.00
103%
ENGINEEREngineering & Reports(8)$15000.00$27200.00-$12200.00
181%
SURVEYSurveys(2)$5000.00$8000.00-$3000.00
160%
CONCRETEConcrete & Slab(3)$85000.00$72500.00$12500.00
85%
PLUMBINGPlumbing(3)$60000.00$59500.00$500.00
99%
ELECTRICALElectrical(2)$55000.00$55000.00$0.00
100%
EXCAVATIONExcavation & Earthworks(2)$45000.00$43500.00$1500.00
97%
ROOFINGRoofing(1)$45000.00$42500.00$2500.00
94%
WINDOWSWindows & Doors(1)$40000.00$40000.00$0.00
100%
PLASTERPlastering & Gyprocking(2)$35000.00$34500.00$500.00
99%
HVACAir Conditioning(2)$30000.00$30000.00$0.00
100%
PAINTINGPainting(2)$30000.00$30000.00$0.00
100%
LANDSCAPELandscaping & Driveways(1)$30000.00$30000.00$0.00
100%
TILINGTiling(2)$30000.00$29500.00$500.00
98%
FLOORINGFlooring(2)$25000.00$24500.00$500.00
98%
JOINERYJoinery & Wardrobes(1)$20000.00$18000.00$2000.00
90%
GLASSGlass & Shower Screens(3)$20000.00$17826.20$2173.80
89%
INSULATIONInsulation(1)$15000.00$14000.00$1000.00
93%
WASTEWaste & Skip Bins(4)$15000.00$12705.00$2295.00
85%
WATERPROOFWaterproofing(1)$12000.00$12000.00$0.00
100%
FENCINGFencing(1)$12000.00$11000.00$1000.00
92%
INSURANCEInsurance & HBCF(1)$8000.00$7272.73$727.27
91%
GARAGEGarage Doors(1)$6000.00$5500.00$500.00
92%
BATHROOMBathroom Fixtures & Tapware(2)$20000.00$15800.00$4200.00
79%
SITESite Establishment(2)$10000.00$7000.00$3000.00
70%
DRIVEWAYDriveways & Paving(1)$15000.00$5500.00$9500.00
37%
CLEANINGCleaning(1)$6000.00$4500.00$1500.00
75%
Total$887000.00$1074258.49-$187258.49121%

Job Details

Client
John Smith
Status
active
Start
1 Nov 2025
Est. Completion
30 June 2026

Invoices (74)

Citywide Cleaning Services

Final Clean - 42 Smith St Both UnitsCLEANING

$4500.00

Jemena Gas

Gas Connection - 42 Smith StUTILITIES

$4000.00

Review

Ausgrid

Permanent Power ConnectionUTILITIES

$7000.00

Review

Hanson Concrete

Driveway Concrete - 42 Smith StDRIVEWAY

$5500.00

Review

Green Thumb Landscapes

Colorbond Fencing - 42 Smith StFENCING

$11000.00

Review

Green Thumb Landscapes

Landscaping & Driveway - 42 Smith StLANDSCAPE

$30000.00

Review

Blue Commercial Bin

Waste Bin Service - Final CleanWASTE

$2310.00

Review

Spark Electrical Contractors

Electrical Fit-Off - 42 Smith StELECTRICAL

$20000.00

Review

AJ Plumbing Services

Plumbing Fit-Off - 42 Smith St Both UnitsPLUMBING

$20000.00

Review

Kwik Glass Greenacre Pty Ltd

Frameless Shower Screen - Unit BGLASS

$7590.00

Review

Choices Flooring Marrickville

Flooring Supply & Install - Unit BFLOORING

$12000.00

GLASS PRO AUSTRALIA PTY LTD

Glass Hardware - Rose Gold FittingsGLASS

$2364.20

Review

Kwik Glass Greenacre Pty Ltd

Frameless Shower Screen - Unit AGLASS

$7872.00

Review

Choices Flooring Marrickville

Flooring Supply & Install - Unit AFLOORING

$12500.00

ProCoat Painting

Painting Labour - 42 Smith St Both UnitsPAINTING

$24000.00

Inner West Wardrobe Co

Built-In Wardrobes - Both UnitsJOINERY

$18000.00

Dulux Trade Centre

Paint Supply - 42 Smith StPAINTING

$6000.00

Reece Plumbing

Bathroom Fixtures + Kitchen Sink - Unit BBATHROOM

$7800.00

Caesarstone AU

Benchtops - 42 Smith St Both UnitsKITCHEN

$19000.00

Cut Above Kitchens

Kitchen Cabinetry - 42 Smith St Unit BKITCHEN

$17500.00

+ 54 more